The hot-work permit must coordinate ship and yard: permission to enter a space does not mean welding or cutting is permitted inside it.

hot work permitfire watchshipyarddry dock safety

Operational Explanation

Define activity, location, duration, responsibilities and interactions with other work before starting. Required certification depends on local law, space type and previous contents; designation of an officer in the SMS does not replace a legally required qualification or authorisation.

Regulatory Reference

Apply local law, the yard permit system and ship SMS. MSC.581(110) addresses enclosed-space entry. The US example OSHA: hot-work testing, 29 CFR 1915.14 distinguishes Marine Chemist and Shipyard Competent Person responsibilities; it is not a universal rule for every yard.

As a good-practice reference, IMCA HSS032 / M221 Rev. 2, August 2025, section 5.5 addresses firefighting readiness and dedicated hot-work fire watches; 6.2–6.2.1 addresses coordination of ship/yard permits and simultaneous operations. The guidance does not replace local law, authorizations or the SMS. Define the duration and conditions of the post-work watch in the agreed system. IMCA — Guidance on safety in shipyards, Rev. 2.

Scope of Application

Welding, cutting and other ignition-producing activities during repairs. Also assess adjacent spaces, opposite sides of surfaces, connections, residues and coatings; separately coordinate any enclosed-space entry.

Procedure / How to Complete It

  1. Identify required authorisations and ship, yard and contractor responsibilities.
  2. Define the task and permit validity, checking interactions with other work.
  3. Arrange isolation and checks of atmosphere, residues and connected spaces against applicable hot-work criteria.
  4. Check ventilation, fire watch, communications and response equipment.
  5. Stop if conditions change; have them reassessed and obtain the necessary reauthorisation before resuming.
  6. Close the permit only after the required checks and post-work watch.

Practical Example

Ventilation fails during cutting: stop the task, make it safe and request reassessment before resuming. A test at the start of the shift does not establish that conditions remained safe. OSHA: changing hot-work conditions.

What Typically Goes Wrong

Using entry readings as hot-work authorisation, ignoring adjacent spaces or continuing after conditions change.

Common Mistakes Mistake Library

MistakeHow to avoid it
Using entry readings as hot-work authorisation, ignoring adjacent spaces or continuing after conditions change.Check the individual ship’s requirements and documents before closing the work.

What the PSCO Checks

Ship PSC checks may concern SMS procedures, permits, isolations and management of observed unsafe conditions. They do not replace the authority responsible for yard occupational safety and authorisations. Keep coordination and anomaly handling traceable.

Operational Tips

Preparation checklist

FAQ

Does safe for entry mean safe for hot work?
No. The two authorisations have different purposes and conditions.
May an SMS-designated officer always certify?
Only if the law and permit system authorise that person for the specific activity.
How long must the post-work watch last?
Follow applicable law, the permit and risk assessment; do not adopt one duration as a worldwide rule.