Permit to Work System
A Permit to Work is the documented method by which the SMS controls high-risk work under the applicable procedure and risk assessment.
Operational Explanation
A Permit to Work is a documented method adopted by the SMS to control high-risk work. ISM §7 requires procedures for key operations but does not prescribe one PTW model, seven categories, or universal thresholds and durations.
Regulatory Reference
ISM Code §7: the Company establishes procedures, plans and instructions for key operations. Categories, atmospheric limits, signatories and validity derive from risk assessment, SMS and applicable sector guidance. SOLAS III/19.3.6 concerns entry and rescue drills, not the source of an enclosed-space permit.
A permit documents controls already verified at the worksite; it does not replace risk assessment, energy isolation, verification of zero energy, monitoring, supervision and coordination of simultaneous work. Before reinstatement check people, tools, safeguards and handback of the system. National practical guidance, to be applied in its proper context: MCA COSWP 2026.
Scope of Application
Work subjected by the ship's SMS to PTW control according to risk, ship, cargo, location and applicable guidance; there is no uniform IMO list of seven permits.
Procedure / How to Complete It
- Identify the work and applicable SMS procedure.
- Apply thresholds, signatories, validity, isolation and monitoring required by company procedure and relevant guidance.
- Suspend and reassess when conditions, people or scope change.
- Close the permit and restore the system under the procedure.
Practical Example
Example: for hot work, atmospheric limits, signatories, fire watch and validity are taken from the SMS procedure and applicable guidance; the permit is suspended if conditions change.
What Typically Goes Wrong
Common Mistakes Mistake Library
| Mistake | Consequence | How to avoid it |
|---|---|---|
| Hot work permit renewed without a new atmosphere test if the work extends beyond the initial validity | Risk conditions not updated, possible accident with an atmosphere that has changed in the meantime | Always repeat the atmosphere test when renewing a hot work permit |
| Multiple permits active at the same time without checking their mutual interactions | Unforeseen risk combinations (e.g. hot work and bunkering in the same area) | Always check all active permits before authorising a new one |
| Cold work in a hazardous area started without assessing the controls required by the SMS | Activities with real risks (e.g. painting in a confined space) carried out without adequate controls | Always apply the SMS risk assessment and controls; use a formal PTW where the SMS or applicable sector guidance requires it |
What the PSCO Checks
Operational Tips
- Always repeat the atmosphere test when renewing a hot work permit, don't rely on the initial test.
- Always check the interaction between all active permits before authorising a new one.
- For cold work in hazardous areas always apply the SMS risk assessment and controls; use a formal PTW where prescribed.
Preparation checklist
- SMS procedure and risk identified
- Thresholds and signatories taken from applicable source
- Validity and reassessment defined
- Isolation and monitoring checked
- Close-out and restoration documented