Managing Shipyard Repair Contracts

The repair specification, tender and contract must follow project complexity, risk, market and ship due dates; REPAIRCON 2018 is a contract form, not a universal docking timeline.

repair contractshipyardBIMCO RepairConshipyard

Operational Explanation

The contract allocates scope, price, time, responsibility, insurance, variations, tests, delivery, warranty and disputes. Preparation must start early enough for the actual project; intervals such as 6, 9 or 12 months are planning examples, not mandatory standards.

BIMCO REPAIRCON 2018 is a standard ship-repair form that can be adapted. The form, rider clauses, law and jurisdiction should be reviewed together by technical, procurement and competent advisory functions.

Regulatory Reference

No IMO convention prescribes a repair-contract form or timeline. The cited contractual reference is BIMCO REPAIRCON 2018; the signed contract, applicable law and statutory/class requirements governing the work control.

In the REPAIRCON 2018 sample, clause 5(c) connects redelivery with necessary inspections and tests; the signed protocol identifies agreed work to be completed afterwards. Operational records should assign each outstanding task an owner, deadline and acceptance check. Always check amendments and riders in the signed contract. REPAIRCON 2018 sample, clause 5(c).

In the sample, 5(c)(iii) requires the yard to rectify defects at its cost before redelivery unless the owners agree that certain work may be completed afterwards. A punch list alone does not authorize deferral: document the agreement and identify outstanding work in the redelivery and acceptance protocol under 5(c)(iv).

Scope of Application

Repairs and conversions placed with a yard. Internal responsibility and approval authority follow Company organization and contract; they do not universally belong to one role.

Procedure / How to Complete It

  1. Define scope, standards, drawings, inclusions, exclusions and acceptance criteria.
  2. Check yard capability, availability, subcontractors and interfaces.
  3. Compare bids on a common basis and clarify extra-work rates.
  4. Negotiate variations, delay, liability, insurance, payment, warranty and disputes.
  5. Define authority, records, hold points, tests and close-out.

Practical Example

For steel renewal, the specification defines areas, grade, tolerances, NDT, class attendance and acceptance criteria; the bid separates base scope from unit rates for added quantities found after opening.

What Typically Goes Wrong

Ambiguous scope or uncoordinated clauses turn each discovery into a dispute over price, time and responsibility. A fixed start date does not compensate for incomplete specifications.

Common Mistakes Mistake Library

MistakeConsequenceHow to avoid it
Timeline presented as a standardFalse assurancePlan from the actual critical path
Form used without adaptationRisks not allocatedCoordinate form, riders and applicable law

What the PSCO Checks

PSC does not interpret the private repair contract; it checks ship compliance and applicable documents. Contract acceptance does not prove regulatory compliance.

Operational Tips

Preparation checklist

FAQ

Does REPAIRCON prescribe when planning must start?
No. Timing follows the project and ship due dates.
Which BIMCO edition is cited?
REPAIRCON 2018.
Is the standard form sufficient without riders?
Not necessarily; it must be adapted to scope, risk and applicable law.