SuperbaKnowledge Demonstration release
Platforms
ENIT
Operational guide · Operational procedure

Heavy Lift Cargo and Project Cargo

Heavy lift and project cargo require reliable data and an engineering package consistent with the CSM and ship limits; Annex 13 authorises neither autonomous crew calculations nor a universal independent sea-fastening survey.

heavy liftproject cargoCSS Code Annex 13special cargoes

Operational Explanation

Annex 13 provides design assumptions and an assessment method for semi-standardised and non-standardised cargo. The arrangement must nevertheless be covered by the approved CSM or engineering/case-specific analysis prepared by competent personnel and accepted or approved as required. Deck/tank-top limits, stability, grillage, support and sea fastening remain part of the engineering package.

Regulatory Reference

SOLAS VI/5.6; MSC.1/Circ.1623 — CSS Annex 13. The approved CSM and engineering package govern securing. Operational procedures for weather-dependent securing must be documented in the approved CSM or SMS under Annex 13 §7.1.6, consistently with applicable limits. A forecast alone does not authorize arbitrary design-load reductions.

IMO — SOLAS II-1/3-13, effective 1 January 2026. Separately verify applicable lifting-appliance requirements: design, operation, inspections, testing and maintenance. A lifting plan does not replace sea-fastening design, or vice versa.

Scope of Application

Heavy lift, out-of-gauge and project cargo require assessment proportionate to mass, geometry, supports, CoG, structure and voyage. Approval/acceptance and independent survey depend on Administration, class, CSM, Company, contract, charterer or insurer; they are not identical universal IMO duties for every cargo.

Procedure / How to Complete It

  1. Obtain reliable mass, dimensions, verified CoG, support and lifting points from the shipper.
  2. Check deck/tank-top limits, stability, structural loads and compatibility with the approved CSM.
  3. Have competent personnel prepare securing/sea-fastening analysis under Annex 13 and other applicable standards.
  4. Obtain acceptance/approval and survey where required by documents and competent parties.
  5. On board verify installation against drawings and calculations; stop on discrepancy.

Practical Example

For a turbine on deck, the engineering package checks supports, grillage, deck loads, stability, design accelerations and sea fastening. Weather or speed limits apply only if formally included. Crew verify installation against accepted drawings.

What Typically Goes Wrong

Dividing weight by the whole deck area hides concentrated support reactions. Competent engineering must check load paths, grillage and supporting structure. Lifting points are not automatically suitable as securing points: directions and capacities must be checked for each use.

Common Mistakes Mistake Library

MistakeConsequenceHow to Avoid It
Improvised onboard Annex 13 calculationStructural assessment and acceptance process are missingUse competent engineering and approved/accepted package
Forecast freely reduces design loadsArrangement falls outside approved assumptionsUse weather-dependent limits only where formally prescribed
Independent survey treated as universal IMO dutyRequirement unsupported by the sourceCheck contract, insurer, Company, class and Administration

What the PSCO Checks

Consistency between approved CSM/engineering package and actual arrangement, cargo data, structural/stability limits, acceptance conditions and familiarisation. Design responsibility is not transferred to crew.

Operational Tips

Preparation checklist

FAQ

May crew autonomously design securing with Annex 13?
No. Use an arrangement in the CSM or engineering package prepared by competent personnel and accepted/approved as required.
May forecast reduce design loads?
Only within weather-dependent procedures and limits formally prescribed in the CSM/engineering package.
Is an independent sea-fastening survey always required?
No. Check contract, insurer, Company, class and Administration.
What did the 2020 revision do?
It introduced and clarified the criteria of the revised Annex 13; it is not a future proposal.

Related Topics

Last substantive revision of this page: 15 September 2026 · page fingerprint dedde402f247